SECTION 4 - MARINE MEASUREMENT
หน้าแรก
คำชี้แจง
- ถ้าไม่กรอกทั้งชื่อ และนามสกุลของผู้ทำข้อสอบ ระบบจะไม่ตรวจข้อสอบให้
- ถ้าทำข้อสอบไม่ครบ ระบบจะไม่ตรวจข้อสอบให้
- เกณฑ์ตัดสินผ่านการทดสอบอยู่ที่ร้อยละ 90 หรือ 27 ข้อขึ้นไป
กรอกชื่อจริง
กรอกนามสกุล
แบบทดสอบนี้ มีจำนวนข้อสอบ 89 ข้อ หากต้องการเพิ่มจำนวนข้อ ให้เลือก เพิ่มจำนวนข้อเป็น 20 ข้อ 30 ข้อ 50 ข้อ
1. 4.01 If the vessel incurs an in transit loss of product and an in transit gain in water, what action should be taken?
    a. Obtain samples of the free water
    b. Check the vessel s bunkers and bunker consumption during the voyage
    c. Verify the condition of seals on the sea suction and overboard discharge valves
    d. Answers a., b. and c. are all correct
2. 4.82 Independent inspectors are not expected to correct barge tank gauges/dips for trim because most barges do not have trim tables.
    a. True
    b. False


3. 4.13 What is the purpose of ballast?
    a. To keep the cargo warm
    b. To segregate cargoes
    c. To reduce the ship s fuel consumption
    d. To maintain the vessel s stability, trim and draft, and to control vessel stress
4. 4.71 During a tank entry inspection, which of the following is not correct?
    a. Since more than one person will be entering the tank, it is not necessary to have a standby person at the hatch
    b. All pipelines should be drained and verified empty
    c. The tank atmosphere should be tested for safe entry
    d. All surface areas should be checked for possible contamination, tank coating condition and loose rust
5. 4.29 If possible, should you seal a vessel s cargo system sea-valves or any equivalent connection to the ballast system prior to loading?
    a. No
    b. Yes


6. 4.72 When wall washing a tank, which of the following is correct?
    a. Tank bottoms (floor) normally do not require wall washing
    b. There are two wall wash methods, blotter and funnel
    c. Each wall wash area should be at least 3 feet by 6 feet
    d. Answers a., b. and c. are all correct
7. 4.69 What must be determined at a pre-loading tank inspection key meeting between vessel s personnel, shore personnel and inspection personnel?
    a. Tank number, tank capacity, intended cargo volume
    b. The last three cargoes and method of tank cleaning
    c. The contents of adjacent tanks
    d. Information a., b. and c. must all be determined
8. 4.38 What is the Reference Gauge Height of a vessel tank?
    a. The overall height of the expansion trunk, referred to in the drawings
    b. The distance from the tank bottom to the reference gauge point as specified on the tank s capacity table
    c. The measured distance from the tank bottom to the reference gauge point
    d. The place inside the tank where automatic measurement floats are installed
9. 4.65 What should the number of areas in a cargo tank to be wall washed be based upon?
    a. The last cargo
    b. The tank capacity
    c. The amount of wall wash medium you have
    d. The age of the vessel
10. 4.36 What term is used for the measurement of cargo through two or more openings in a tank?
    a. Repetitive motion gauging
    b. Duplicate gauging
    c. Multi-point gauging
    d. Hatch survey
11. 4.83 What should an inspector do if asked to sign a Dry Certificate:
    a. Sign it if reasonably sure the tanks are dry
    b. Sign it if the ship s crew confirms that the tanks are dry
    c. Refuse to sign as per IFIA guidelines
    d. None of the above
12. 4.86 What does API MPMS Chapter 17.9 / EI HM 49 cover:
    a. Temperature
    b. Sampling
    c. Vessel Experience Factors
    d. Gauging
13. 4.37 What is a Charter Party?
    a. A traditional event hosted by the owner of a vessel celebrating the vessel being hired
    b. A document specifying the dimensions of a vessel so it can get into the docks to load and unload its cargo
    c. A document outlining the terms and conditions that will apply to the owner and the charterer while a vessel is on hire
    d. A statement of the demurrage to be charged to the charterer
14. 4.18 Why may multipoint gauging be required when performing an OBQ/ROB survey?
    a. To help determine if a wedge condition exists
    b. To help determine the nature (liquid or non-liquid) and quantity of the OBQ/ROB
    c. Because the vessel is on even keel.
    d. Answers a. and b. are correct
15. 4.56 What is freeboard on a vessel?
    a. The distance from the waterline to the vessel s deck level
    b. The distance from the waterline to the vessel s keel
    c. The time when local Customs officials permit others to board the vessel
    d. The time of day that lay time begins according to the Charter Party
16. 4.80 According to Energy Institute HM28 / HM29 API MPMS Chapter 17.1, what should happen as part of a shore inspection?
    a. The Terminal should tell the Inspector the condition of the line
    b. A line fullness verification procedure should be requested to verify line condition
    c. Unless instructed otherwise, the Inspector should assume that the line is full before and after transfer of product
    d. Answers a., b. and c. are all correct
17. 4.42 What is meant by the term trimmed by the head?
    a. The aft draft reading is greater that the forward draft reading.
    b. The forward draft reading is greater than the aft draft reading.
    c. The ship has water in the forepeak tank.
    d. Trim corrections will always be added to the measured gauge
18. 4.89 When calculating a VEF, only the most recent twenty voyages should be used:
    a. True
    b. False


19. 4.54 Typically, four parties receive samples at the loading port when a marine tank vessel is loaded. Three of those parties are (1) the independent inspector, (2) the vessel for delivery to the discharging terminal, (3) The vessel for retain. Who is the fourth party?
    a. The cargo owner
    b. The vessel for retain
    c. The vessel s agent
    d. The load port terminal
20. 4.14 When should a bunker inspection be performed?
    a. Only with fuel oil cargoes
    b. With every product except gasoline
    c. When requested by the vessel
    d. As appropriate or on the request of the principal
21. 4.27 What is the amount of material found in a tank after discharge called?
    a. Slops
    b. On Board Quantity (OBQ)
    c. Bunkers
    d. Remaining On Board (ROB)
22. 4.44 What is the main reason for taking draft readings on fully-loaded vessels at the loading port?
    a. To be used at the discharge port in case of a cargo variance
    b. To enable calculation of trim or list corrections if needed
    c. To compare with draft readings at the discharge port
    d. To ensure adequate cargo drainage
23. 4.64 What is a wipe test?
    a. The procedure of wiping sample containers to ensure they are clean before being submitted to the laboratory
    b. The procedure of physically wiping a tanks interior surface with absorbent white rags to test for possible contamination
    c. A specialized laboratory test for the presence of water, iron, polymers and emulsion
    d. Answers a., b. and c. are all wrong
24. 4.39 As a minimum, how many liquid level measurements must be taken in a vessel s tanks when the vessel is in motion (rolling)?
    a. 2
    b. 3
    c. 4
    d. 5
25. 4.08 When you are on board a marine vessel, the overall responsibility for the use of proper safety procedures, appropriate measurement equipment and the correct sampling equipment rests with?
    a. The inspector
    b. The inspection company that the inspector works for
    c. The vessel
    d. The inspection company s principal
26. 4.84 It is acceptable for an inspector to sign Dry Certificates, Vessel Cleanliness certificates showing that cargo tanks are suitable for the intended cargo, ROB certificates with pumpability statements, and pumping logs.
    a. True
    b. False


27. 4.40 Is the holding of a key meeting prior to an inspection required to comply with Industry Standards
    a. Yes
    b. No


28. 4.53 When should a wedge formula calculation be used on a vessel trimmed by the stern?
    a. When liquid material does not contact the forward bulkhead
    b. When solid material is gauged at a single gauge point
    c. When free water completely covers the tank bottom
    d. Answers a., b. and c. are all correct
29. 4.26 What is the amount of material found in a tank prior to loading called?
    a. Slops
    b. On Board Quantity (OBQ)
    c. Bunkers
    d. Remaining On Board (ROB)
30. 4.31 If there is spotting of the water paste above the clear cut level what would you use to calculate the volume?
    a. The very top of the spotting
    b. The clear cut but note the spotting volume in the remarks
    c. There is no mention of spotting in published standards
    d. Answers a., b. and c. are all wrong
ให้ตรวจสอบชื่อนามสกุลว่ากรอกครบหรือไหม่
พร้อมกับตรวจข้อสอบว่าเลือกทำครบทุกข้อหรือไม่ ไม่ครบไม่ตรวจนะครับ
แนะนำชุดข้อสอบ

1. วิชาเอก (ชีววิทยา)


2. บทที่ 6 การใช้งานแผงโซล่าเซลล์


3. ระบบเศรษฐกิจ ป.4


4. ภาษาอังกฤษ ชั้นมัธยมศึกษาปีที่ 3


หน้าแรก

EDUCATION RESEARCH | Test Home
Version Thaitestonline.com | Mobile
เพื่อนบ้านเว็บครูออฟ